Captive Energy CPC Plant
Ghana
- Sector:
- Clean Energy
- Sub-sector:
- Renewable Energy based on CHP Technology for 5MW
- Type of project:
- BOOT contract with CPC the off-taker
Total project cost:
$32M
Total raise:
$29Min equity & Debt
Problem:
Project stalled with previous investors on policy interpretation
Solution:
Dhaxle conducted investment readiness process and partnered with Dixie (UAE) and WealthBullet (UK/UAE) to arrange revenue based funding for 120 months. 10 September, 2024.